Project background and challenges
In order to improve the stability and reserve capacity of the water supply system of the Juwan Electrolytic Aluminum Project in Indonesia and cope with uneven water demand, our company undertook the construction project of this key vertical cylindrical steel welded storage tank. The core goal of the project is to build a large-scale water storage facility with strong structure and excellent sealing performance to serve as the core buffer and reserve unit in the regional water supply network.


Solutions and Implementation
The project uses high-standard carbon steel materials and strictly follows relevant international design and construction specifications. Through precise plate rolling process and automated welding technology, the roundness of the tank and the long-term sealing of the weld are ensured. The overall design focuses on structural strength and anti-corrosion performance to adapt to the local environment and ensure the safety of water storage quality. The project team overcame challenges such as on-site coordination and process control, and finally completed the main body construction and related testing of the tank with high quality.


Project results and value
The successful completion of the storage tank marks a critical upgrade of the local water supply infrastructure. It not only significantly improves the storage and regulation capabilities of regional raw water, provides reliable guarantee for daily and peak water use, but also enhances the resilience of the entire water supply system to cope with emergencies. This project demonstrates our company’s professional strength in the design, manufacturing and construction of large steel storage tanks, and also accumulated valuable experience for overseas livelihood infrastructure construction projects.







Back